A medical or dental fitout in Sydney costs between about $2,200 and $4,500 per square metre in 2026, excluding GST, clinical equipment and base-building work. Infection control, accessibility, specialised plumbing and electrical, and the approvals that go with a health use push it above office rates — and a dental surgery with its chairs, compressor and suction sits at the top of the band.
| Level of finish | $ per m² | Program on site |
|---|---|---|
| Basic | 2,200–2,800 | 8–10 weeks |
| Mid | 2,800–3,500 | 10–14 weeks |
| Premium | 3,500–4,500 | 14–20 weeks |
Per m² of floor area, design and construct, excluding GST, equipment and base-building work. Under 80 m² add about 15%.
Existing services kept, consult rooms partitioned, vinyl floors, hand basins added where drainage exists, reception counter, basic lighting. Allied health and GP rooms.
New partitions with acoustic rating, new lighting, hydraulics to every consult room, treatment room with medical gas or compressed air rough-in, accessible WC, reception joinery.
Dental and specialist: surgeries with chair plumbing, suction and compressor plant, lead-lined radiology, sterilisation room to AS/NZS 5667, full mechanical, bespoke reception.
| Floor area | Basic | Mid | Premium |
|---|---|---|---|
| 100 m² | $220,000 – $280,000 | $280,000 – $350,000 | $350,000 – $450,000 |
| 200 m² | $440,000 – $560,000 | $560,000 – $700,000 | $700,000 – $900,000 |
| 400 m² | $880,000 – $1,120,000 | $1,120,000 – $1,400,000 | $1,400,000 – $1,800,000 |
All-in design-and-construct ranges from the September 2026 rates. Run your own floor area through the calculator.
Medical is where approvals bite. A medical centre replacing a medical centre can be complying development, but a shop or office becoming a medical centre is a change of use that usually needs a DA, with parking and traffic the usual sticking points. Allow 8–16 weeks and start the approval before the lease starts, not after.
Exempt, CDC or DA — the full guide · DA or CDC · Change of use
| Trade | Share | On a 200 m² mid-finish job |
|---|---|---|
| Hydraulics to every room | 16% | $101,000 |
| Partitions, acoustic and doors | 16% | $101,000 |
| Mechanical, medical gas and plant | 16% | $101,000 |
| Electrical, lighting and data | 14% | $88,000 |
| Joinery, reception and sterilisation | 14% | $88,000 |
| Floors, finishes and accessibility | 10% | $63,000 |
| Design, approvals and preliminaries | 14% | $88,000 |
Typical split of a mid-finish price; the shares move with the building and the brief. Excludes GST.
| Type | Where it sits | Why |
|---|---|---|
| GP or allied health rooms | Basic to mid | Consult rooms, a basin in each, accessible WC, reception. The lower half of the medical band. |
| Physio, chiro, psychology | Basic | Fewer basins, treatment rooms, often a former office: the cheapest health use to fit out. |
| Dental surgery | Premium | Chair plumbing, suction and compressor plant, sterilisation to AS/NZS 5667, often radiology. |
| Specialist or day-procedure rooms | Premium | Medical gas, higher mechanical, clinical finishes and a more demanding approval. |
| Medical centre in a former shop | Mid to premium | Change of use to a medical centre: a DA, parking assessment and an accessible path of travel retrofit. |




In Sydney in 2026, about $150,000 to $250,000 per surgery once chair plumbing, suction, compressor plant, sterilisation and the share of reception and waiting are counted, before the chair and equipment themselves.
Usually, if the premises were not a medical centre before: a change of use to a health use brings parking and traffic into the assessment. A medical centre replacing a medical centre can be complying development.
Basins in every consult room, sealed and coved floors, a dedicated sterilisation room with one-way flow, and clinical-grade joinery. It is the main reason medical sits above office rates.
For a health use, in practice yes. An accessible WC and an accessible path of travel from the street are required under the NCC and the Disability Discrimination Act, and retrofitting them into an older building is a real line in the budget.
Eight to ten weeks on site at basic finish, ten to fourteen at mid, fourteen to twenty for a dental or specialist job. A DA adds eight to sixteen weeks before that.