A childcare centre fitout in Sydney costs between about $2,000 and $4,200 per square metre of indoor area in 2026, excluding GST, outdoor play areas, loose furniture and base-building work. The size is set by the National Quality Framework — 3.25 m² of unencumbered indoor space and 7 m² of outdoor space per child — so a 60-place centre needs roughly 250–300 m² of indoor playrooms before the cot room, kitchen, staff room, laundry, nappy-change and office are added.
| Level of finish | $ per m² | Program on site |
|---|---|---|
| Basic | 2,000–2,600 | 10–14 weeks |
| Mid | 2,600–3,300 | 14–18 weeks |
| Premium | 3,300–4,200 | 18–24 weeks |
Per m² of floor area, design and construct, excluding GST, equipment and base-building work. Under 80 m² add about 15%.
An existing approved centre refreshed: paint, floors, child-height joinery replaced, bathroom fittings, lighting, acoustic panels. No change to room layout or services.
Re-planned playrooms with new partitions and acoustic doors, new children's bathrooms and nappy-change, kitchen and laundry re-fit, new lighting and mechanical rebalancing.
New centre in a shell: full design to the Child Care Planning Guideline, new hydraulics to every playroom bathroom, commercial kitchen, laundry, mechanical throughout, indoor-outdoor thresholds, fencing and soft-fall to the outdoor area.
| Floor area | Basic | Mid | Premium |
|---|---|---|---|
| 300 m² | $600,000 – $780,000 | $780,000 – $990,000 | $990,000 – $1,260,000 |
| 600 m² | $1,200,000 – $1,560,000 | $1,560,000 – $1,980,000 | $1,980,000 – $2,520,000 |
| 900 m² | $1,800,000 – $2,340,000 | $2,340,000 – $2,970,000 | $2,970,000 – $3,780,000 |
All-in design-and-construct ranges from the September 2026 rates. Run your own floor area through the calculator.
Childcare always needs approval. A new centre, or a change of use into one, is a development application assessed against the Child Care Planning Guideline and SEPP (Transport and Infrastructure) 2021, then a service approval from the NSW Department of Education before it can open. Allow 4–8 months for the DA and start it before committing to the lease. Alterations inside an existing approved centre can go through a private certifier.
Exempt, CDC or DA — the full guide · DA or CDC · Change of use
| Trade | Share | On a 600 m² mid-finish job |
|---|---|---|
| Partitions, acoustic and doors | 14% | $248,000 |
| Nappy change, kitchen and hydraulics | 16% | $283,000 |
| Mechanical, fire and safety glazing | 16% | $283,000 |
| Outdoor play and soft fall | 14% | $248,000 |
| Joinery, storage and cot rooms | 12% | $212,000 |
| Floors, finishes and fencing | 12% | $212,000 |
| Design, approvals and preliminaries | 16% | $283,000 |
Typical split of a mid-finish price; the shares move with the building and the brief. Excludes GST.
| Type | Where it sits | Why |
|---|---|---|
| Small centre, under 40 places, existing building | Basic to mid | Rooms, nappy change, kitchen and a small outdoor area; the Department of Education service approval still applies. |
| Centre in a purpose-built shell | Mid | Services and outdoor play designed in; the fitout is rooms, joinery and finishes. |
| Conversion of a former office or church hall | Mid to premium | Change of use DA, fire upgrade, outdoor play built from nothing, acoustic separation. |
| Large centre, 80 places and up | Premium | Multiple age-group rooms, commercial kitchen, staff areas, extensive outdoor play and shade. |
| Out-of-school-hours care | Basic | Fewer wet areas and no cot rooms; usually within a school. |




Roughly $8,000 to $15,000 per licensed place in 2026 for the fitout alone, excluding the building, land and the outdoor play construction, which can be as much again on a conversion.
Yes, almost always, and the Department of Education service approval runs alongside it. Allow four to eight months for the two together; the Child Care Planning Guideline sets the floor areas and outdoor space the DA is assessed against.
3.25 m² of unencumbered indoor space and 7 m² of outdoor space per child under the National Regulations, plus the rooms the service approval requires: nappy change, kitchen, laundry, staff and storage.
Outdoor play construction and shade, acoustic separation between rooms, the number of wet areas, safety glazing throughout, fencing, and the fire upgrade on a conversion.
Eight to twelve weeks on site for a centre in a purpose-built shell, longer on a conversion. The approvals before that are the long part: four to eight months for the DA and service approval together.
Send the floor area, the address and a few photos. City Fitouts walks the site and comes back with one fixed price for design, construction and approvals.